15% Off!

NEC4: Engineering and Construction Subcontract
Stock Status: In Stock (Only 1 left)
£67.20
Excl. Tax:
£67.20
£57.49
(No VAT Payable)
Excl. Tax:
Excl. Tax:
The NEC4: Engineering and Construction Subcontract (ECS) is intended for use in appointing a subcontractor where the contractor has been appointed under the NEC4 Engineering and Construction Options, the available secondary options, schedules of cost components and contract data.
The NEC4 Engineering and Construction Subcontract uses clear and professional language, thus promoting fair dealing and greater certainty, as do all NEC4 Contracts.
Core Clauses
1 General
2 The Subcontractor’s main responsibilities
3 Time
4 Quality management
5 Payment
6 Compensation events
7 Title
8 Liabilities and insurance
9 Termination
Â
Main Option Clauses
Option A: Priced subcontract with activity schedule
Option B: Priced subcontract with bill of quantities
Option C: Target subcontract with activity schedule
Option D: Target subcontract with bill of quantities
Option E: Cost reimbursable subcontract
Â
Resolving and Avoiding Disputes
Option W1
Option W2
Â
Secondary Option Clauses
Option X1: Price adjustment for inflation (used only with Options A, B, C and D)
Option X2: Changes in the law
Option X3: Multiple currencies (used only with Options A and B)
Option X4: Ultimate holding company guarantee
Option X5: Sectional Completion
Option X6: Bonus for early Completion
Option X7: Delay damages
Option X8: Undertakings to the Client or Others
Option X9: Transfer of rights
Option X10: Information modelling
Option X11: Termination by the Contractor
Option X12: Multiparty collaboration (not used with Option X20)
Option X13: Performance bond
Option X14: Advanced payment to the Subcontractor
Option X15: The Subcontractor’s design
Option X16: Retention
Option X17: Low performance damages
Option X18: Limitation of liability
Option X20: Key Performance Indicators (not used with Option X12)
Option X21: Whole life cost
Note Option X19 is not used
Option Y(UK)1: Project Bank Account
Option Y(UK)2: The Housing Grants, Construction and Regeneration Act 1996
Option Y(UK)3: The Contracts (Rights of Third Parties) Act 1999
Option Z: Additional conditions of subcontract
Â
Schedule of Cost Components
Short Schedule of Cost Components
Subcontract Data
Part one – Data provided by the Contractor
Part two – Data provided by the Subcontractor
Index
Description
The NEC4: Engineering and Construction Subcontract (ECS) is intended for use in appointing a subcontractor where the contractor has been appointed under the NEC4 Engineering and Construction Options, the available secondary options, schedules of cost components and contract data.
The NEC4 Engineering and Construction Subcontract uses clear and professional language, thus promoting fair dealing and greater certainty, as do all NEC4 Contracts.
Core Clauses
Main Option Clauses
Resolving and Avoiding Disputes
Secondary Option Clauses
The NEC4 Engineering and Construction Subcontract uses clear and professional language, thus promoting fair dealing and greater certainty, as do all NEC4 Contracts.
Core Clauses
- 1 General
- 2 The Subcontractor’s main responsibilities
- 3 Time
- 4 Quality management
- 5 Payment
- 6 Compensation events
- 7 Title
- 8 Liabilities and insurance
- 9 Termination
Main Option Clauses
- Option A: Priced subcontract with activity schedule
- Option B: Priced subcontract with bill of quantities
- Option C: Target subcontract with activity schedule
- Option D: Target subcontract with bill of quantities
- Option E: Cost reimbursable subcontract
Resolving and Avoiding Disputes
- Option W1
- Option W2
Secondary Option Clauses
- Option X1: Price adjustment for inflation (used only with Options A, B, C and D)
- Option X2: Changes in the law
- Option X3: Multiple currencies (used only with Options A and B)
- Option X4: Ultimate holding company guarantee
- Option X5: Sectional Completion
- Option X6: Bonus for early Completion
- Option X7: Delay damages
- Option X8: Undertakings to the Client or Others
- Option X9: Transfer of rights
- Option X10: Information modelling
- Option X11: Termination by the Contractor
- Option X12: Multiparty collaboration (not used with Option X20)
- Option X13: Performance bond
- Option X14: Advanced payment to the Subcontractor
- Option X15: The Subcontractor’s design
- Option X16: Retention
- Option X17: Low performance damages
- Option X18: Limitation of liability
- Option X20: Key Performance Indicators (not used with Option X12)
- Option X21: Whole life cost
- Option Y(UK)1: Project Bank Account
- Option Y(UK)2: The Housing Grants, Construction and Regeneration Act 1996
- Option Y(UK)3: The Contracts (Rights of Third Parties) Act 1999
- Option Z: Additional conditions of subcontract
- Schedule of Cost Components
- Short Schedule of Cost Components
- Subcontract Data
- Part one – Data provided by the Contractor
- Part two – Data provided by the Subcontractor
- Index
Product Information
ISBN | 9780727762115 |
---|---|
Publication Status | Current |
Publication Date | 22/06/2017 |
Format (Paperback, Hardback etc) | Paperback |
Brand / Publisher | NEC |
Publisher | ICE Publishing |
Delivery
We offer customers a wide range of delivery options from Free (7-10 working days) ... right up to by Next Day by 9am (subject to location and stock availability).
- Simply choose your preferred service when checking out
- We show "live" stock levels for all publications
- Orders received after 3:45pm will be processed on the next working day.
- Unless specifically requested, our delivery partners will not attempt a weekend delivery
Returns
We offer all customers a "No Quibble" 28 day returns policy.
If you need to return a title for any reason ...
- Contact our customer services team first to explain what you are returning and the reason
- Request a Returns Authorisation Number
- We will email you this and a link to arrange your return quickly & easily via Royal Mail
- Take your return to your nearest Post Office and they will do the rest
Please refer to our Returns page for full details & charges.